Quick answer. An as-built survey measures what was actually built, once the work is done, to produce a drawing or model that replaces design intent with reality. What matters is not the instrument but three decisions made before the survey: timing (a pipe is surveyed before backfill, not after), reference (the project’s coordinate system and vertical datum) and the tolerance required for each element. For utilities and civil works, total stations and GNSS remain the foundation; for a building or a complex facility, 3D scanning captures everything visible in one pass. Require the deliverable to state what was measured, what was inferred, and how accuracy was checked.
“As-built drawings are required for acceptance of the work.” For a contractor, that line often arrives at the end of a job, when everything is already backfilled, closed in or painted. For a building manager, the same question comes up years later, when the original drawings no longer match what is in front of them. In both cases, the as-built survey is the record of what really exists. Scoped well, it closes a project cleanly and serves for decades. Scoped poorly, it gets redone, or worse, it misleads the next person who digs or drills in the wrong place.
What is an as-built survey?
It is the field measurement of a structure as it was actually built: position, elevations, dimensions, and elements added or moved during construction. An image helps separate it from the design drawings. The design is the planned route; the as-built is the GPS track of the trip actually taken, detours included.

Three notions are often confused:
- The as-built survey is the measurement work: points, elevations, a point cloud, tied to a known reference.
- The as-built drawing (called a “plan TQC” in Quebec) is the document that comes out of it: a 2D drawing, often in DWG and PDF, or a BIM model of the completed work.
- Redlines are the corrections a contractor marks by hand on the working drawings during construction. Useful, but they are not measurements: they say an element moved, rarely exactly where it ended up.
An as-built survey is not a certificate of location either. In Quebec, the certificate of location is reserved to land surveyors (arpenteurs-géomètres): it states a property’s situation in relation to titles, boundaries and regulations. The as-built survey documents a structure for design, acceptance, operation or maintenance. A project can require both; they answer different questions.
When do you need an as-built survey?
Four situations account for most requests:
- At acceptance of the work. Municipalities and public owners often require as-built drawings of utilities and structures before accepting work, especially under municipal works agreements for new developments. The exact requirements (format, coordinate system, deadline) vary from one city to the next: check the specification or the applicable by-law.
- At the end of a building project. The owner needs an accurate record to operate, maintain and modify the building.
- Before a renovation or an expansion. The original drawings exist but no longer match reality. The existing conditions are surveyed so design starts from a reliable base.
- In a dispute. A measured, dated record settles things faster than an argument over redlines.
Timing: you cannot measure what is already buried
This is the most expensive mistake, and it has nothing to do with technology. A scanner, a total station or a drone only sees visible surfaces. A backfilled pipe, a conduit cast into a slab or a duct closed behind drywall will never appear in the survey if nobody measured it at the right time.
On a utility job, the as-built survey is therefore done in stages, with the trench open: manhole inverts, pipes, service connections, bends and fittings are measured before backfill. In a building, the same logic applies to elements that will be hidden: survey visits are planned before ceilings are closed or slabs are poured. This schedule is set with the contractor at the start of the work, not the day before acceptance.

The Canadian standard CSA S250 (Mapping of underground utility infrastructure), whose second edition from 2020 was reaffirmed in 2025, points the same way for underground infrastructure: it recognizes LiDAR and total station surveys as data collection methods, sets requirements for absolute positioning (horizontal and vertical datums) and specifies accuracy requirements for as-builts. It also makes record keeping mandatory throughout the life of the utility.
Which method for which structure?
The right method follows from the structure, the tolerance and the access, not from a preferred instrument. Most of the time, methods are combined.
| Structure | What is measured | Usual method | Critical moment |
|---|---|---|---|
| Water, sewer and storm networks | Inverts, manholes, pipes, service connections | Total station or GNSS, tied to the control network | Open trench, before backfill |
| Roads, curbs, earthworks | Profiles, levels, limits of work | GNSS, total station; drone LiDAR over large areas | End of each stage (subgrade, paving) |
| Building (structure, envelope, fit-out) | Walls, openings, levels, visible elements | Terrestrial 3D scanning or indoor mobile mapping | Before ceilings and walls are closed, then at the end |
| Mechanical room, dense facility | Piping, ducts, equipment | Terrestrial 3D scanning from fixed stations | After installation, before insulation |
| Existing utilities to locate | Position of buried services | Ground-penetrating radar and locating, then test holes as needed | Before design or excavation |
For existing utilities that can no longer be seen, the ASCE 38-22 standard ranks the reliability of information in four quality levels, from QL-D (existing records only) to QL-A (service exposed and measured directly). A drawing that mixes these levels without saying so gives a false sense of certainty.
What to require in the specification
A “compliant” as-built drawing that does not say how it was produced is worth little. Here is what an owner should ask for:
- The reference. The project’s coordinate system (in Quebec, often MTM on NAD83(CSRS)) and the vertical datum. CGVD28 and CGVD2013 still coexist: a drawing that does not state which one it uses is a source of error.
- The tie-in. The survey must be tied to a known control network so it overlays the design drawings and future surveys (see the role of georeferencing).

- Tolerance, element by element. A sewer invert, a facade and a ceiling do not have the same requirements. The tolerance drives the method, not the other way around.
- Measured or inferred. Each element should be flagged as observed in the field or taken from drawings. This is also what the BIMForum LOD Specification requires for existing elements (LOD 500), which must state their accuracy (see which level of development to specify).

- Design vs. as-built comparison. For a building or a bridge, a deviation map between the design model and the survey shows at a glance what falls outside tolerance.
- Formats. DWG and PDF for drawings, IFC or native format for a model, E57 or LAS for the point cloud, with the survey date.
- Verification. How was accuracy checked (independent control points, closure, deviations)? The accuracy a manufacturer advertises is not the accuracy of the deliverable (see the true accuracy of a point cloud).
Accuracy is not an option to be sold as an extra. Delivering what the project needs, and demonstrating it, is part of the job.
Typical case: water and sewer networks in a new subdivision
A representative, anonymous typical case: a developer builds the streets and utilities of a new residential sector under a municipal works agreement.
- The challenge. The city requires georeferenced as-built drawings of pipes, manholes and service connections before accepting the work. Trenches close as the work progresses.
- The approach. A survey schedule is set with the contractor from the start: a survey visit for each section laid, trench open. Inverts, manholes and connections are measured with a total station or GNSS, tied to the same control network used for layout. Deviations from the design are logged as the work advances.
- The logical outcome. An as-built drawing ready at the end of the work, in the city’s required system, with no verification digging after the fact.
Typical case: documenting an institutional expansion
A second typical case: an institution completes the expansion of a building and wants an accurate record for operations and future changes.
- The challenge. Several changes were made in the field; the redlines are incomplete. The mechanical room is dense.
- The approach. Indoor mobile mapping to cover large spaces quickly, terrestrial scanning from fixed stations for the mechanical room and facades, a drone for the roof, all tied to the same control network. A survey visit took place before the ceilings were closed to document the plenums. The point cloud feeds 2D drawings or a model, depending on the intended use.
- The logical outcome. A dated record that separates what was measured from what was inferred, and a reliable base for the next project.

The most expensive mistakes
- Surveying too late. What is buried or closed in cannot be measured without demolition or digging.
- Relying on redlines. They flag a change, not its position.
- Not stating the reference. A drawing in the wrong system, or with no declared vertical datum, overlays nothing.
- Asking for “as accurate as possible” everywhere. Cost rises with no added value; a tolerance per element is better (see what drives the cost of a 3D survey).
- Confusing detailed with correct. A highly detailed model that is poorly tied in shows the wrong reality with great confidence.
How Topo3D carries out an as-built survey
The as-built survey sits where our two core trades meet: construction surveying and 3D scanning. Based in the Montreal area and working across Quebec, we put method ahead of the instrument:
- Read the requirements of the specification, the city or the owner: reference, format, tolerance, deadline.
- Plan survey visits with the contractor, to measure what will be hidden before it is.
- Choose and combine sensors: total station and GNSS for utilities and roads, a terrestrial scanner (including a RIEGL VZ-600i) where tolerances are tight, mobile mapping (NavVis VLX) for large interiors, drone LiDAR for large areas. For existing services, underground infrastructure locating with ground-penetrating radar completes the survey.
- Tie everything to the project’s control network.
- Produce the required deliverable (as-built drawing, point cloud, model, deviation map), with AI agents assisting point cloud analysis under a specialist’s supervision.
- Have the data validated by a technical lead before delivery.
When the as-built survey is part of broader construction monitoring, it combines with site supervision.
In the field. In 2018, Topo3D provided construction surveying on Dickson Street in Montreal for Demix Construction and produced the as-built plans for the provisional acceptance of the City’s work. From 2020 to 2023, it provided construction surveying for buildings A, B and C of the Maestria complex, two towers of 58 and 61 storeys downtown.
Conclusion
A successful as-built survey is decided before anyone reaches the site: the right timing, the right reference and the right tolerance. For utilities and civil works, total stations and GNSS remain the foundation; for a building or a dense facility, 3D scanning captures everything visible and allows design and as-built to be compared. In every case, require a deliverable that states what was measured, what was inferred and how accuracy was checked. That is what turns an end-of-job document into a reliable reference for decades to come.
FAQ
The design drawing shows what was meant to be built. The as-built shows what was actually built, measured in the field, including changes made during construction.
In Quebec, the certificate of location is reserved to land surveyors and states a property’s situation in relation to titles, boundaries and regulations. The as-built survey documents a structure (utility, building, road) for acceptance, operation or design.
With the trench open, before backfill. Once the pipe is buried, it can no longer be measured directly without excavating. The survey schedule is set with the contractor at the start of the work.
No. For utilities and roads, total stations and GNSS are often the best-suited method. 3D scanning pays off for buildings, dense facilities and complex structures, where it captures everything visible in one pass.
It depends on the use: DWG and PDF for as-built drawings, IFC or native format for a BIM model, E57 or LAS for the point cloud. In every case, require the coordinate system, the vertical datum and the survey date.
It depends on the method, the site conditions and the tolerance required for each element. Rather than a general figure, ask for a tolerance per element and the verification method: independent control points and documented deviations.
Do you need to deliver as-built drawings for acceptance of the work, or document a building as it was built? Send us the specification or the city’s requirements, the schedule and the design drawings: we will propose a survey schedule and a suitable method. Let’s talk about your as-built survey.
References
- CSA Group (2020, reaffirmed 2025). CSA S250:20 — Mapping of underground utility infrastructure. https://www.csagroup.org/fr/store/product/2427902/
- ASCE (2022). ASCE/UESI/CI 38-22 — Standard Guideline for Investigating and Documenting Existing Utilities. https://ascelibrary.com/doi/book/10.1061/9780784415870
- BIMForum (2025). Level of Development (LOD) Specification, Part I — 2025. https://bimforum.org/LOD/
- Ordre des arpenteurs-géomètres du Québec. Le certificat de localisation. https://oagq.qc.ca/certificat-de-localisation/