OUR PROJECTS · ROADS AND STRUCTURES
In 2012, for Construction Cyvex, Topo3D laid out the abutments of the P-2 footbridge and the City of Blainville's multi-use trail, then surveyed the anchor bolts after the pour.
CONTEXT
In 2012, the City of Blainville had a multi-use trail built, including a footbridge, the P-2. The work was awarded to Construction Cyvex, based on engineering drawings prepared for the City. During construction, a change notice moved the footbridge abutments and the adjacent path.
OUR MANDATE
For Construction Cyvex, Topo3D provided construction surveying for the P-2 footbridge and the multi-use trail from August to October 2012. The team prepared layout data from the drawings, then laid out the two abutments and the trail alignment. After the change notice, the abutments and the path were laid out again according to the revised drawings. Once the concrete was poured, Topo3D surveyed the centre of the anchor bolts and the face of the bearing walls to confirm conformity before the footbridge was installed.
DELIVERABLES