Édicule nord (édicule Du Collège) reconstruit, qui abrite les ascenseurs

Photo: Jeangagnon (CC BY-SA 4.0, via Wikimedia Commons)

OUR PROJECTS · PUBLIC TRANSIT

Du Collège Station: surveying and scanning for two elevators

ClientCeleb Construction ltée
OwnerSociété de transport de Montréal (STM)
LocationSaint-Laurent, Montreal (QC)
Period2017-2018

In 2017-2018, Topo3D scanned Du Collège metro station in Montreal and laid out two new elevators for general contractor Celeb Construction, on an STM project.

CONTEXT

Opened in 1984 on the Orange Line in the Saint-Laurent borough, Du Collège station serves about 10,000 people a day. The STM made it universally accessible: the north entrance building, closed in February 2017, was rebuilt, and two elevators now link the street to the mezzanine and both platforms. They have been in service since May 2018. The project offset the planned temporary closure of Côte-Vertu station.

OUR MANDATE

For Celeb Construction, the general contractor, Topo3D provided technical and construction surveying for the two new elevators. The existing concrete entrance building, its support beam and its main column left little room: the team surveyed the area around the entrance, scanned the station from the entrance down to the under-platform level and analyzed clashes between the existing structure and the planned elevators. It then positioned the new steel structure and laid out formwork and mechanical elements on four levels.

BY THE NUMBERS

  • 2 elevators laid out
  • Layout on 4 levels

DELIVERABLES

  • Topographic survey around the entrance building
  • 3D scan of the station, from the entrance to the under-platform level
  • Clash analysis between the existing structure and the elevators
  • Layout of the steel structure, formwork and mechanical elements