La passerelle Éva-Dulude et le déversoir du barrage sur la Yamaska, au printemps 2021

Photo: Claude Hébert, L’Avenir et des Rivières (2021)

OUR PROJECTS · MUNICIPAL

Éva-Dulude Dam: 3D survey and bathymetry in Farnham

ClientCity of Farnham
OwnerCity of Farnham
LocationFarnham, Yamaska River
Period2025 to 2026

In 2025-2026, Topo3D surveyed the Éva-Dulude Dam and the Yamaska River in Farnham with bathymetry and LiDAR for the Town of Farnham, to support work planning.

CONTEXT

The Éva-Dulude Dam, a concrete gravity control structure 100 m long and 6.9 m high built in 1956 on the Yamaska River, is owned by the City of Farnham (Répertoire des barrages). In 2021, the City chose to upgrade the dam and the Éva-Dulude footbridge, an option supported by 81% of the 844 residents surveyed (L’Avenir et des Rivières).

OUR MANDATE

Documentation of the upstream reservoir and of the riverbed downstream of the dam to support work planning and hydraulic analyses. Hybrid survey: GPS pole in shallow water, single-beam echo sounder and RTK GPS on a light boat, and LiDAR of the visible surfaces of the dam, the walls and the Saint-Paul Street bridge. Production of a 3D model of the dam, walls, riverbed and bridge.

BY THE NUMBERS

  • About 500 m upstream and 100 to 300 m downstream surveyed
  • Cross-sections every 20 m

DELIVERABLES

  • XYZ point file
  • Point clouds
  • 3D DWG model, LOD 200
  • Technical report