Starting in 2021, Topo3D used a total station to lay out elements on slabs and formwork, columns and stairs of HEC Montréal's Hélène-Desmarais building downtown, for Magil Construction.
CONTEXT
Designed by Provencher Roy, the Hélène-Desmarais building brought HEC Montréal downtown, to 501 De La Gauchetière Street West, at the corner of Côte du Beaver Hall. Magil Construction was the general contractor and WSP the project manager. The building welcomed its first cohorts in August 2023 and was inaugurated on September 15, 2023.
OUR MANDATE
For Magil Construction, Topo3D provided construction surveying on the Hélène-Desmarais building site starting in 2021, with a surveyor dispatched as the work progressed. Using the up-to-date CAD drawings provided by the contractor, he laid out with a total station the elements on slabs and formwork, including those of the level 2 slab, as well as the columns and stairs, the skylight and elements of the René-Lévesque Boulevard facade.
DELIVERABLES