From 2023 to 2026, Topo3D laid out the works and carried out the as-built survey of Henri-Bourassa Boulevard in Saint-Laurent for De Sousa and then Pronex, to City of Montreal requirements.

CONTEXT

The City of Montreal is rebuilding Henri-Bourassa Boulevard between Pitfield Boulevard and Félix-Leclerc Avenue in Saint-Laurent, over about 1.5 km, from spring 2023 to summer 2026. The project includes a rebuilt roadway with three lanes in each direction, wider sidewalks, mid-level bike lanes, bus platforms and pedestrian refuges, along with rehabilitation of the water mains.

OUR MANDATE

Construction surveying for the contractor, De Sousa in 2023 and then Pronex, which took over the contract in 2024: layout of the works during construction, then an as-built survey of the final surfaces, paving and curbs, to the City of Montreal’s requirements for as-built plans. The 2025 surveys were delivered in December; the rest of the survey, impossible under snow, was postponed to spring 2026.

BY THE NUMBERS

  • Section of about 1.5 km

DELIVERABLES

  • Layout of the works
  • As-built survey of the final surfaces