ClientSNC-Lavalin
OwnerQuebec Ministry of Transportation and Sustainable Mobility (MTMD)
LocationHighway 20, from Belœil to A-30; Louis-H.-La Fontaine Tunnel area
Period2017

In 2017, Topo3D carried out night-time mobile LiDAR scanning of Highway 20, from the Richelieu River to A-30, and service roads for SNC-Lavalin, for the MTMD widening study.

CONTEXT

The MTMD is widening Highway 20 over about 13 km between Sainte-Julie and Belœil, within the existing right-of-way, with a reserved lane between A-30 and the Richelieu River. Construction began in 2022 and full commissioning is scheduled for 2027.

OUR MANDATE

For SNC-Lavalin, night-time mobile LiDAR scanning of A-20 from the Richelieu River to A-30, along with service roads, for the widening study (bus lane). Also, complete scanning of the Montreal Island side of the Louis-H.-La Fontaine Tunnel area for preliminary engineering of the ramp reconfiguration.

BY THE NUMBERS

  • 15 km of A-20 surveyed at night
  • 8.4 km of service roads surveyed

Equipment: Leica Pegasus 2

DELIVERABLES

  • Mobile LiDAR point clouds by sector
  • Corridor imagery
  • ReCap or LAS delivery