Scanner laser dans le caisson du pont de l'Île-aux-Tourtes

Photo: Topo3D

OUR PROJECTS · ROADS AND STRUCTURES

Île-aux-Tourtes Bridge: post-tensioning, surveying and 3D scanning

ClientConstruction Interlag inc. and CNPIAT; EXP in 2016-2017
OwnerQuebec Ministry of Transportation and Sustainable Mobility (MTMD)
LocationÎle-aux-Tourtes Bridge (A-40), Vaudreuil-Dorion / Senneville
Period2016 to 2026

From 2016 to 2026, Topo3D monitored tensioning operations and surveyed and scanned the Île-aux-Tourtes Bridge (A-40) for Construction Interlag, CNPIAT and EXP, on behalf of the MTMD.

CONTEXT

The Île-aux-Tourtes Bridge on Highway 40 is reaching the end of its service life. The MTMD is replacing it with a new structure built north of the existing bridge, a design-build-finance project carried out by Groupe Nouveau Pont Île-aux-Tourtes (Dragados Canada, Roxboro Excavation and Construction Demathieu & Bard). A first structure is scheduled to open at the end of 2026.

OUR MANDATE

On the old bridge: 3D scans of the girders and real-time monitoring of tensioning operations (2016), then, during strengthening work, camber surveys before, during and after each tensioning with same-day reports, 3D surveys of the girders for the design of the reinforcements, slab surveys and georeferenced marking. For the new bridge: scanning of footings and annotated elevation drawings.

BY THE NUMBERS

  • 18 km of georeferenced marking completed in one weekend
  • 25 footings of the new bridge scanned
  • Camber monitored on spans T5 to T28

DELIVERABLES

  • Point clouds and 3D meshes of the girders
  • Tensioning and camber control sheets
  • Slab survey plans and paving point lists
  • Georeferenced marking
  • Point clouds and plans of the new bridge footings