In 2020, Topo3D deployed a site survey crew to Hydro-Québec's La Vérendrye substation to support the work on site, starting in the summer.
CONTEXT
In October 2020, the Régie de l’énergie authorized Hydro-Québec to replace the two static var compensators (SVCs) at La Vérendrye substation, with commissioning scheduled from 2022 to 2024.
OUR MANDATE
Starting in summer 2020, Topo3D provided the site survey crew at Hydro-Québec’s La Vérendrye substation, supporting the work carried out on site.
DELIVERABLES