In 2024-2025, Topo3D laid out the platforms, columns, canopy and track at Lucien-L'Allier station in Montréal for general contractor Tisseur, on behalf of exo.
CONTEXT
exo’s Lucien-L’Allier station closed on April 1, 2024, for the complete reconstruction of its four platforms, the addition of a canopy and two emergency exits, and the extension of a track. Trains returned in December 2024.
OUR MANDATE
For Tisseur, the general contractor, Topo3D laid out the platforms, columns and canopy, track and emergency exits at Lucien-L’Allier station. Topo3D also provided construction surveying to Tisseur for structural reinforcement work at Central Station in 2024-2025.
BY THE NUMBERS
DELIVERABLES